The Build Timeline

Discover more about how Westcombe was created into what it is today, from old house into a luxury holiday let overlooking the Salcombe estuary.

Westcombe Build Timeline

2015
Planning Begins

Planning for the redevelopment of Westcombe and the Boathouse initially began in 2015 when we approached Stephen Guard of Stephen Guard Architects.

2017
Planning Submitted

The planning application was submitted in March 2017, however given the property's prominent location in Batson creek, it took nearly 3 years to receive approval on the redevelopment.

December
2019
Planning Granted

Finally, in December 2019 we were granted planning permission for the new property. However, due to the conditions placed on the planning permission it would be another 8 months until we were finally able to commence with the demolition phase of the project.

November
2020
Demolition Begins

In November 2020, demolition finally commenced on the old property. Given the large amount of asbestos cladding on the property we engaged specialists Gilpin Demolition to carry out the demolition. In just 4 weeks the team was able to safely remove and dispose of the asbestos before demolishing the old property to the ground.

January
2021
Creating a New Home

Whilst the demolition of our ancestors' home was met with a touch of sadness given the love they had for it, we are delighted to finally be able to commence with the construction of the new property, and hopefully make them proud.

February
2021
Ground Works Commence

In February, the ground works commenced on the main house and the scaffold was erected on the Boathouse.

March
2021
Boathouse rebuild begins

In March, worked started on rebuilding the Boathouse

April
2021
Foundations Poured

In April, work began on pouring the foundations for the house.

May
2021
Construction of the walls begins

In May, work commenced on constructing both the internal and external walls of the house.

June
2021
Boathouse steels installed

In June, the structural steels for the boathouse were installed and work continued on the construction of the walls of the house.

June
2021
Boathouse second floor construction progresses

Later in June, work progressed on constructing the second floor of the Boathouse.

July
2021
Ground floor internal walls completed

At the start of July, the internal walls on the ground floor were completed, allowing us to get a space of the interior spaces.

July
2021
Boathouse terrace construction begins

Towards the end of july, work began on constructing the boathouse terrace and internal stone feature wall.

August
2021
Internal Staircase built

In August, the main internal concrete stairs were installed and work continued on the boathouse terrace.

September
2021
Stone Cladding commences

In September, work began on cladding the ground floor with the beautiful grey stone.

October
2021
Boathouse terrace completed

At the start of October, the boathouse terrace was completed and the yellow cedar cladding installed. Work also commenced on the first fix in the boathouse.

November
2021
Ground Floor construction begins

In November, following the instalation of the block and beam ceiling, we we're finally able to commence with the construction of the ground floor floor.

November
2021
Roof construction begins

In late November, the roof timbers and steels were installed on the main house

December
2021
Scaffolding and sheeting goes up

At the end of the year, the house was covered in sheeting allowing for the roof to be insulated and tiling to commence.

Janaury
2022
Roof completed

At the start of the year the tiling of the roof was completed and the solar panels installed.

February
2022
Screed poured

Early in February, the screed was poured on the lower ground ready for the flooring to be installed.

March
2022
Pool Shell completed

In March, the pool shell was completed ready for rendering and tiling

View Build Gallery 
+
No items found.
Top